+ 359 2 4748 800 info@gcr.bg

Photovoltaic Power Plant in Water World – Bankya

Photovoltaic Power Plant Water World – Bankya Overview Employer:Voden Svyat – Bankya AD duration:Jun 2023 – Aug 2023 Project site The installed peak power of the Photovoltaic Power Plant (PPP) is 12.6kWp, and the capacity of the local energy storage...

Open Switchgear 31.5kV Substation Maritsa East

Open Switchgear 31.5kV Substation Maritsa East Overview Employer:KMS EOOD duration:Mar 2023 – Sep 2023 Budget:75 000 EUR Project site The work project covers the construction of two new fields in the 31.5kV substation for the connection of two new shunt...